Written by: Dawda Baldeh
An investigation by Gambian news outlet The Republic has revealed how a $165 million agreement to build a major power plant in The Gambia collapsed after the government failed to secure the financing needed to implement the project, leaving behind unanswered questions about the deal and its financial implications.
The investigation, published on October 29th, found that the National Water and Electricity Company (NAWEC) signed a $165.6 million construction contract with Chinese state-owned engineering giant Sinohydro Corporation in April 2017, shortly after President Adama Barrow assumed office.
The agreement was intended to address The Gambia’s chronic electricity shortages through the construction of a 62-megawatt heavy fuel oil power plant in the Greater Banjul Area, alongside new electricity transmission lines.
At the time, NAWEC officials celebrated the agreement as a “game-changer” for the country’s energy sector. However, nearly a decade later, construction has never commenced, and the promised power plant remains unrealised.
According to The Republic, the arrangement originated under former President Yahya Jammeh’s administration, which signed an initial memorandum of understanding with Sinohydro on July 13th, 2015. The Barrow administration subsequently advanced the project, signing a formal Engineering, Procurement and Construction (EPC) contract valued at $165,628,710.40.
But the investigation uncovered a major weakness in the agreement: NAWEC had signed the construction contract without securing the financing required to pay for it.
The contract stipulated that the project would only become fully effective once NAWEC obtained the necessary funding. Sinohydro was also entitled to a 30% advance payment, approximately $49.6 million, before commencing work.
Without the financing and initial payment, the project never progressed beyond the planning stage.
A former senior NAWEC official involved in the negotiations told The Republic that the government struggled to meet certain financial conditions, including a possible sovereign guarantee that would have required the state to assume NAWEC’s financial obligations in the event of default.
The official also explained that international financiers generally demanded competitive bidding, whereas the Sinohydro agreement involved single-source procurement.
“The financiers then would always request competitive bidding, and in this case, the recruitment was to be single-sourcing,” the official said.
The investigation further established that the contract contained provisions granting Sinohydro extensive tax exemptions while placing responsibility for land acquisition, resettlement costs and compensation on NAWEC. It also included financial penalties for delayed payments.
Former Minister of Petroleum and Energy Fafa Sanyang, who oversaw the agreement and now serves as The Gambia’s Ambassador to the United Arab Emirates, attributed the project’s failure to funding difficulties.
“The Sinohydro agreement was intended to be an EPC project. However, no loan agreement or contract was signed, and the project could not be pursued due to funding related issues,” his office told The Republic.
His assertion that no contract was signed contradicts the EPC agreement examined by the investigative outlet.
The investigation also exposed difficulties in obtaining official records of the project.
Responding to an Access to Information request dated October 12th, 2026, NAWEC Managing Director Gallo Saidy acknowledged that the utility was still searching for documents relating to the agreement.
He explained that “internal enquiries are ongoing to establish the availability and location of the historical records” across relevant departments, citing the age of the project.
Meanwhile, the Ministry of Petroleum, Energy and Mines failed to respond to the outlet’s information request, while attempts to obtain clarification from Sinohydro through its parent company, PowerChina, and its regional office were unsuccessful.
The investigation also examined the financial implications of The Gambia’s subsequent reliance on Turkish electricity supplier Karpowership, which provided power to the national grid under a separate agreement.
According to The Republic, payments to Karpowership reached approximately $200 million by the time its contract ended in May 2025, exceeding the proposed cost of the Sinohydro power plant. Unlike a completed power plant, the arrangement did not leave NAWEC owning the generating equipment.
The findings raise broader questions about the management of major public infrastructure agreements, particularly the decision to sign an expensive construction contract before securing the financing required for implementation.
Nine years after the Sinohydro agreement was celebrated as a solution to The Gambia’s electricity problems, the promised power plant remains unbuilt, with questions persisting over the project’s contractual obligations, financial consequences and the government’s handling of its collapse.